FDOT starts Cortez Bridge replacement work in Bradenton Beach
The 0.9-mile project will proceed in two phases, with the first phase building the northern half next to the current structure.
By Mei Chen ·

The 0.9-mile Cortez Road Bridge Replacement Project started on Monday, Nov. 16, marking the beginning of a multi-year construction effort. The work zone spans from 123rd Street West in Cortez to Gulf Drive in Bradenton Beach. A crane mounted on a work barge was positioned on the northeast side of the bridge to drive a test piling as operations commenced.
The Florida Department of Transportation will build the new bridge in two distinct phases. In the first phase, crews will construct the northern half of the new bridge directly adjacent to the existing structure. Once that section is finished, traffic will shift onto the new bridge. This move will allow workers to demolish the old bridge and begin building the southern half of the new span.
Initial activities are focused on pile-driving operations and force main utility work along the Hunters Point property. Construction crews will operate between 7 a.m. and 6:30 p.m. on weekdays. Occasional nighttime and weekend work is also planned to keep the project on schedule.
Motorists, pedestrians, and bicyclists should expect intermittent lane closures, periodic shoulder closures, and temporary traffic shifts during the daytime and at night. Drivers must obey posted signage and watch for construction vehicles entering and exiting the roadway. The Intracoastal Waterway will stay open to boaters, and the current drawbridge opening schedule remains in effect.
The project is expected to be completed in summer 2030. The department has directed residents to the project website for updates and detailed information on the work schedule.