City Commission Approves $159,000 In Final Pier Repairs
Three change orders for doors, heating, and pumping systems were ratified Nov. 17, moving the Anna Maria City Pier closer to a mid-December reopening.
By Mei Chen ·

The Anna Maria City Commission unanimously approved three change work orders totaling approximately $159,000 during a special meeting on Nov. 17. The approvals cover the installation of a new heating and cooling system, a waste pumping unit, and a set of visual coiling doors for the pier buildings.
Mayor Mark Short reported that the city has $6.93 million in confirmed funding for the reconstruction project. The total project cost is set at $6.93 million, which includes a contingency reserve of $246,599. Short stated that $5.55 million in costs has been incurred to date. This figure includes $4.64 million for walkway replacement and infrastructure, $559,927 for demolition and engineering, and $354,530 for T-end demolition, remediation, and finishing work.
The city has requested $4.63 million in reimbursements so far. That amount includes $2.03 million from the Federal Emergency Management Agency, the full $1.25 million state appropriation, and $1.35 million from Manatee County. Short noted that the city has received $2.26 million in actual payments. This total comprises $913,312 from FEMA and $1.35 million from the county. The state has not yet paid out its allocated funds.
An additional $778,231 in work is currently under contract. This includes $556,811 for T-end finishing and project management, and $221,420 for walkway and infrastructure improvements. The open items for the project total $350,000. These costs cover the HVAC system, lift station pumps, the roll-up visual door system, and pier lighting. The city is reissuing a request for proposals for the lighting components.
The Nov. 17 vote approved a $53,995 increase with Southern Cross Contracting for the door system. The doors will be installed in three of the four exterior walls of the larger pier building. The commission also approved an $86,135 order for the HVAC system and an $18,680 proposal from Barney’s Pumps for the waste processing equipment at the T-end.
The pier suffered damage from Hurricane Helene in September 2024. Hurricane Milton then destroyed most of the walkway less than two weeks later. The walkway had been rebuilt in 2020 after Hurricane Irma damaged the structure in 2017.
Business owners Brian Seymour and Ben Sato toured the T-end buildings after the Nov. 12 commission meeting. They lease the space for their PIERadise restaurant operations. The large building, previously occupied by Mote Marine, will serve as the main dining area. The smaller building, formerly the City Pier Grill, will house the kitchen. Seymour said the visual doors will allow for an open-air dining environment while the roll-up hurricane shutters provide protection during storms.
Sato said the hurricane shutters are scheduled for delivery on Nov. 18, while the visual doors are expected in early January. The owners hope to open the pier to the public by mid-December. Seymour said the reopening aims to restore foot traffic to nearby Pine Avenue businesses, which have struggled since the hurricanes.
More News · Bradenton news · Report a business · Got a Story?