700 Megawatts: Former GOP Nominee Urges Governor-Elect to Halt Auburndale Data Center
James Fishback sent a letter to Byron Donalds Thursday, asking the incoming governor to stop the project after a crowded public workshop in the city.
By Mei Chen ·

The proposed Auburndale Technology Center could require up to 700 megawatts of electricity at full capacity, a figure that has drawn the attention of former state Republican gubernatorial nominee James Fishback. Fishback sent a letter to Florida Governor-elect Byron Donalds on Thursday. The letter asks Donalds to publicly oppose the project and use his executive authority to stop it.
The facility would convert two existing warehouse buildings along Pace Road near Florida Polytechnic University into a data center. Developer Hillwood plans the construction in phases. The first phase requires approximately 350 megawatts. Tampa Electric is expected to supply the power. Fishback compared the potential total demand to the electricity used by nearly half a million homes.
Donalds addressed the issue on social media on Tuesday morning before a public workshop in Auburndale. He wrote that his campaign trail statements are his commitment. Donalds stated that if a local community says no data center, then no data center. He added that Florida will protect water, electric bills, and residential neighborhoods.
Fishback said Donalds has an obligation to protect the people of Auburndale. He argued that residents have made their position clear. “Clearly, they do not want this data center,” Fishback said. He asked Donalds to act before the project crosses a point of no return.
Angela Walker, a resident who purchased her property in 1990, said she learned about the proposal last week through social media. She stands at the back fence of her home and sees the proposed warehouse sites directly. “I’m really, extremely frustrated,” Walker said. She bought the property to raise her children and grandchildren there.
Roughly 500 people attended the public workshop on Tuesday night, with hundreds more watching online. Many speakers opposed the plan, citing electricity demand, environmental impact, noise, and effects on nearby homes. Hillwood estimates the facility would use about 4,665 gallons of water per day using a closed-loop cooling system. The developer projects nearly 300 permanent jobs and up to 1,300 construction jobs at peak activity.
Residents questioned why another city vote is not required. Auburndale commissioners approved a future land-use change and Industrial Planned Unit Development zoning for the property in December 2023. This approval happened before Hillwood acquired the site and proposed the data center. City officials say the current zoning permits data centers under technology and research uses.
The city received an application on November 4 for the interior retrofit of the two buildings. Staff are reviewing the plans. The project remains subject to permitting review and approvals from state agencies, including the Southwest Florida Water Management District. Donalds' team had not responded to a request for comment by publication time. Walker said she hopes the governor-elect will intervene before construction begins.